dc.identifier.citation | Abarinda, J. (2021). Towards improving schedule performance of construction projects in Uganda with lean construction. (Unpublished Master's thesis). Makerere University, Kampala. | en_US |
dc.identifier.uri | http://hdl.handle.net/10570/8587 | |
dc.description | A thesis submitted to the Directorate Of Research And Graduate Training in partial fulfillment of the requirements for the award of a Degree of Master of Science in Construction Management of Makerere University. | en_US |
dc.description.abstract | Among the management concepts and methods implemented to improve construction project
schedules is the integration of lean tools in the construction project cycle. Lean is a production
management-based project delivery system emphasizing the reliable and speedy delivery of
value. Uganda’s construction industry faces problems of project delays which affect project
schedules and should be addressed to save time and consequently save costs. However,
application of lean to improve schedule performance in Uganda’s construction industry is
difficult as the industry does not yet fully understand what the concept is about. Lean is
ambiguous, and this makes its application difficult. This research was carried out to understand
the common practices in Uganda’s construction industry, determine the extent of lean application
in the industry and also propose a feasible lean integration strategy to ensure timely completion
of construction projects. The research approach was a mixed approach involving qualitative and
semi quantitative methods; questionnaires and structured interviews were issued to contractors
registered with the contractors’ body in Uganda, to evaluate construction processes, identify gaps
and propose lean tools to address critical factors that affect project schedule performance.
Considering the prevailing practice, lean tools that were found to be easily applicable in Uganda
were value stream mapping, Just in time, use of the last planner and collaborative planning tools.
These could be used to address factors like poor work methods, poor communication and poor
planning among others. A lean integration strategy was proposed to enable companies integrate
these lean tools into their construction processes to improve their adherence to schedules. The
research contributes to the understanding that context in terms of culture and environment cannot
be ignored while implementing lean in construction and that lean tools should be appropriately
prioritized for successful implementation. | en_US |
dc.language.iso | en | en_US |
dc.subject | Construction projects | en_US |
dc.subject | Lean construction | en_US |
dc.subject | Schedule performance | en_US |
dc.title | Towards improving schedule performance of construction projects in Uganda with lean construction | en_US |
dc.type | Thesis | en_US |